STATEMENT SHOWING PROGRESS OF WORKS/SCHEMES UNDER M.P. LOCAL AREA DEVELOPMENT SCHEME
                                                  FOR THE YEAR 2002-2003

 ------------------------------------------------------------------------------------------------------------------------------------------------------
 Name of the M.P SHRI R. KHARSHIING                                                                                          
 ------------------------------------------------------------------------------------------------------------------------------------------------------
   Name of the Block|Year |  Name of the Schemes          |Amount Approved    |  Amount Utilised  |Status/  |Date/Expected |Reasons for delay
                    |     |                               |by MP sanctioned   | As on 31.10.2007  |Position |Date of Comple|in completion
                    |     |                               |  with Date        |                   |of the   |tion          |
                    |     |                               |                   |                   |Scheme   |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|CONST. OF CLASS ROOM ON THIRD  | Rs. 1,00,000.00   | Rs. 1,00,000.00   |COMPLETED|
                    |     |FLOOR OF SYNOD COLLEGE AT      |     07/04/2003    |                   |         |
                    |     |JAIAW SHILLONG                 |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|CONST. OF MAWPAT PLAYGROUND    | Rs. 2,00,000.00   | Rs. 2,00,000.00   |COMPLETED|              |
                    |     |                               |    30/06/2002     |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|CONST. OF MOTORABLE ROAD AT    | Rs.   75,000.00   | Rs.   75,000.00   |COMPLETED|
                    |     |DONG MARBOH (NONGRAH)          |    17/12/2002     |                   |         |              |
                    |     |                               |                   |                   |         |      
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|CONST. OF FOOTPATH AT DONG     | Rs.   30,000.00   | Rs.   30,000.00   |COMPLETED|              |
                    |     |NONGLUM NONGRAH VILLAGE        |    30/06/2003     |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|CONST. OF BORE WELL IN         | Rs.   50,000.00   | Rs.   50,000.00   |COMPLETED|              |
                    |     |AUXILIUM SCHOOL                |    30/06/2003     |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|CONST. OF PUBLIC FOOTPATH      | Rs. 1,78,000.00   | Rs. 1,78,000.00   |COMPLETED|              |
                    |     |ADJACENT TO ART   CULTURE      |                   |                   |         |
                    |     |PRESBYTERIAN                   |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|CONST. OF LANE AT RILBONG      | Rs.   22,000.00   | Rs.   22,000.00   |COMPLETED|
                    |     |STARTING FROM MR. A HAQUE      |                   |                   |         |
                    |     |HOUSE TO MR. M. AHMED          |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|PURCHASE INSTALLATION OF 5     | Rs. 4,40,000.00   |Rs. 3,36,150.00     COMPLETED|              |
                    |     |COMPUTER,HARDWARE SOFTWARE     |                   |                   |         |             
                    |     |SYSTEM, FURNITURE AND TRAINING |                   |                   |        
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|PURCHASE INSTALLATION OF 5     | Rs. 4,40,000.00   | 3,36,150.00       |COMPLETED               |                     
                    |     |COMPUTERS,HARDWARE SOFTWARE    |                   |                   |         |              |
                    |     |SYSTEM,FURNITURE, 2 YEARS      |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|CONST. OF SLAB-DRAIN-CUM FOOT- | Rs. 1,50,000.00   | Rs.  1,50,000.00  |Completed|        
                    |     |PATH AT MAWLAI NONGPDENG,
                    |     |SHILLONG                       |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|CONST. OF RETAINING WALL FOR   | Rs.   50,000.00   | Rs.    50,000.00  |Completed|
                    |     |SACRED HEART BOY'S HIGHER      |                   |                   |         |
                    |     |SECONDARY SCHOOL CAMPUS MAWLAI |                   |                   |         |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|IMPROVEMENT OF WATER SUPPLY    | Rs.   50,000.00   | Rs.   50,000.00   |Completed|
                    |     |AT LAWSOHTUN                   |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|CONST. OF FOOTPATH AT          | Rs.   25,000.00   | Rs.   25,000.00   |Completed|              |
                    |     |LAWSOHTUN                      |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|CONST. OF STAFF QUARTER FOR    | Rs. 2,00,000.00   | Rs. 2,00,000.00   Completed |
                    |     |RILBONG L.P SCHOOL, SHILLONG   |                   |                   |         |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|EXPANSION/CONST. OF SMALL      | Rs.   60,000.00   | Rs.   60,000.00   |Completed|
                    |     |SCALE INDUSTRY CENTRE AT       |                   |                   |         |
                    |     |UPPER MALKI, SHILLONG          |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|CONST. OF SCHOOL AUDITORIUM IN | Rs. 1,00,000.00   | Rs. 1,00,000.00   |Completed|
                    |     |GORKHA PATHSHALA HIGHER        |                   |                   |         |              |
                    |     |SECONDARY SCHOOL, MAWPREM      |                   |                   |         |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mylliem Block     |02-03|CONST. INCLUDING METALLING-CUM | Rs. 2,00,000.00   | Rs. 2,00,000.00   |         |
                    |     |BLACK TOPPING OF ROAD AT RIAT- |                   |                   |Completed|
                    |     |SOHKHLUR 3rd MILE NONGKSEH     |                   |                   |         |
                    |     |UPPER SHILLONG                 |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Shella Block      |02-03|CONST. OF FOOTPATH FROM KATO   | Rs.   50,000.00   | Rs.   50,000.00   |         |
                    |     |LBA SHELLA                     |    30/06/2003     |                   |completed|              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Shella Block      |02-03|CONST. OF PLAYGROUND AT        | Rs. 1,00,000.00   | Rs. 1,00,000.00   |         |              |
                    |     |WAHKALIAR VILLAGE              |                   |                   |Completed|              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Shella Block      |02-03|CONST. OF NEW BUILDING WAHADA- | Rs. 1,00,000.00   | Rs. 1,00,000.00   |Completed|
                    |     |DAR ROBISON SYNGWAN MEMORIAL   |                   |                   |         |
                    |     |HIGH SCHOOL SOHLAP             |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Shella Block      |02-03|CONST. OF HOSTEL FOR CHRISTIAN | Rs. 1,00,000.00   | Rs. 1,00,000.00   |Completed               |
                    |     |CHILDREN HOME(ORPHANAGE) AT    |                   |                   |         |
                    |     |POMSOHMEN                      |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Shella Block      |02-03|CONST. OF OFFICE BUILDING-CUM- | Rs.   50,000.00   | Rs.   50,000.00   |Completed|
                    |     |I.B AT BHOLAGANJ, SOHRA        |                   |                   |         |              |
                    |     |SYIEMSHIP                      |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Shella Block      |02-03|CONST. OF DORBAR HALL IN       | Rs. 2,00,000.00   | Rs. 2,00,000.00   |Completed|
                    |     |HIMA SOHRA                     |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |                  
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Pynursla Block    |02-03|IMPROVEMENT OF FOOTBALL FIELD  | Rs.   30,000.00   | Rs.   30,000.00   |Completed|              |
                    |     |AT PDENGSHNONG WAHSKONG        |                   |                   |                        |
                    |     |NONGJRI                        |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawsynram Block   |02-03|CONST. OF COMMUNITY HALL AT    | Rs.   90,000.00   | Rs.   90,000.00   |Completed|              |
                    |     |MAWKAPHAN VILLAGE              |    25/03/2003     |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawsynram Block   |02-03|CONST. OF CEMENTED FOOTPATH    | Rs.   50,000.00   | Rs.   50,000.00   |Completed|              |
                    |     |FROM PWD ROAD TO PDENGSHNONG   |    25/03/2003     |                   |         |              |
                    |     |MAWRAPAD VILLAGE               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawsynram Block   |02-03|CONST. OF PUCCA CEMENTED FOOT- | Rs.   60,000.00   | Rs.   60,000.00   |Completed|              |
                    |     |PATH CUM-CONST. OF DRAIN BY    |                   |                   |         |
                    |     |THE SIDE OF FOOTBALL PLAY      |                   |                   |      
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawsynram Block   |02-03|CONST. OF PLAYGROUND AT        | Rs. 1,00,000.00   | Rs. 1,00,000.00   |Completed |              |
                    |     |MAWSYNRAM BORDER AREA COLLEGE  |                   |                   |         |
                    |     |CAMPUS                         |                   |                   |         |              |              
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawsynram Block   |02-03|PURCHASE INSTALLATION OF 5     | Rs. 4,40,000.00   | Rs.3,36,000/-     |         |              |          
                    |     |COMPUTERS HARDWARE SOFTWARE    |                   |                   |completed|
                    |     |SYSTEM, FURNITURE&TRAINING     |                   |                   |         |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawsynram Block   |02-03|CONST. OF COMMUNITY HALL AT    | Rs. 2,00,000.00   | Rs. 2,00,000.00   |Completed               |
                    |     |HAT MAWDON                     |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawsynram Block   |02-03|CONST. OF COMMUNITY HALL-CUM-  | Rs. 1,00,000.00   | Rs. 1,00,000.00   |Completed|             |
                    |     |COURT ROOM AT MAWSYNRAM        |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawsynram Block   |02-03|CONST. OF COMMUNITY HALL AT    | Rs. 1,00,000.00   | Rs. 1,00,000.00   |Completed|              |
                    |     |DANGAR DOMBAH                  |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawsynram Block   |02-03|CONST. OF DORBAR HALL AT       | Rs. 1,00,000.00   | Rs. 1,00,000.00   |Completed|              |
                    |     |THYLLAW                        |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|CONST. OF VILLAGE DURBAR HALL  | Rs.   50,000.00   | Rs.   50,000.00   |Completed|              |
                    |     |AT LUMSOHRIEW MAWKALUM VILLAGE |    07/04/2003     |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|CONST. OF SCHOOL BUILDING AT   | Rs. 2,00,000.00   | Rs. 2,00,000.00   |Completed|              |
                    |     |MAWPHLANG PROCEEDING SECONDARY
                    |     |SCHOOL                         |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|PURCHASE INSTALLATION OF 5     | Rs. 4,40,000.00    Rs.3,36,000/-      |Completed|              |
                    |     |COMPUTERS HARDWARE SOFTWARE    |                   |                   |  
                    |     |SYSTEM, FURNITURE AND TRAINING |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|CONST. OF COMMUNITY HALL CUM-  | Rs. 2,00,000.00   | Rs. 2,00,000.00   |Completed|              |
                    |     |INDOOR SPORT HALL AT LUMSOH-
                    |     |KHLUR NONGBAH, SOHIONG         |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|CONST. OF TRAINING CENTRE AT   | Rs. 1,00,000.00   | Rs. 1,00,000.00    Completed|              |
                    |     |MAWPHLANG                      |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|CONST. OF COMMUNITY HALL AT    | Rs. 1,50,000.00   | Rs. 1,50,000.00    Completed|              |
                    |     |MARBISU                        |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|CONST. OF COMMUNITY HALL AT    | Rs. 1,50,000.00   | Rs. 1,50,000.00    Completed|              |
                    |     |MAWPHLANG                      |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|CONST. OF CEMENT PLATFORM TO   | Rs.   20,000.00   | Rs.   20,000.00   |Completed |              |
                    |     |SEAT DRUMMER AND FLUTIST       |                   |                   |          |
                    |     |LAITMAWSHING                   |                   |                   |          |              |
 --------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|CONST. OF COMMUNITY HALL AT    | Rs. 1,50,000.00   | Rs. 1,50,000.00    Completed|              |
                    |     |MARBISU                        |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|CONST. OF COMMUNITY HALL AT    | Rs. 1,50,000.00   | Rs. 1,50,000.00   |Completed|              |
                    |     |MAWPHLANG                      |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|CONST. OF TRAINING CENTRE AT   | Rs. 1,00,000.00   | Rs. 1,00,000.00    Completed|              |
                    |     |MAWPHLANG                      |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|CONST. OF COMMUNITY-CUM-INDOOR | Rs. 2,00,000.00   | Rs. 2,00,000.00   |Completed|              |
                    |     |SPORT HALL AT LUMSOHKHLUR      |                   |                   |         |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|PURCHASE & INSTALLATION 5      | Rs. 4,40,000.00   | Rs.3,36,000/-      Completed               |              
                    |     |CUMPUTERS HARDWARE ETC KYIEM   |                   |                   |         |
                    |     |PROCEEDING HIGH SCHOOL         |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|CONST. OF SCHOOL BUILDING AT   | Rs. 2,00,000.00   | Rs. 2,00,000.00   |         |              |
                    |     |MAWPHLANG PROCEEDING SECONDARY |                   |                    Completed|              |
                    |     |SCHOOL                         |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawphlang Block   |02-03|CONST. OF VILLAGE DURBAR HALL  | Rs.   50,000.00   | Rs.   50,000.00   |Completed|              |
                    |     |AT LUMSOHRIEW MAWKALUM         |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawryngkneng Block|02-03|IMPROVEMENT OF FOOTBALL GROUND | Rs.   25,000.00   | Rs.   25,000.00   |COMPLETED|              |
                    |     |AT KUT VILLAGE(DONG RNGI)
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawryngkneng Block|02-03|CONST. OF COMMUNITY HALL AT    | Rs.   75,000.00   | Rs.   75,000.00   |COMPLETED|              |
                    |     |DONG IEWRIM PURIANG            |    30/06/2003     |                   |         |              |
                    |     |                               |                   |                   |         |              |
 -----------------------------------------------------------------------------------------------------------------------------------------------------
  Mawryngkneng Block|02-03|CONST. OF BUS SHED STOP FOR    | Rs.   25,000.00   | Rs.   25,000.00   |Completed|              |
                    |     |PUBLIC TRANSPORT PASSENGER AT  |                   |                   |         |
                    |     |KUT WAHIINGKIENG               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawryngkneng Block|02-03|CONST. OF BUS SHED STOP FOR    | Rs.   25,000.00   | Rs.   25,000.00    Completed|              |
                    |     |PUBLIC TRANSPORT PASSENGERS
                    |     |AT PURIANG MAWKAJUT            |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawryngkneng Block|02-03|CONST. OF BASKET BALL          | Rs.   50,000.00   | Rs.   50,000.00   |Completed|              |
                    |     |PLAYGROUND COURT AT RISING SUN |                   |                   |         |
                    |     |SCHOOL, MAWRYNGKNENG           |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawryngkneng Block|02-03|IMPROVEMENT OF PLAYGROUND AT   | Rs.   25,000.00   | Rs.   25,000.00   |COMPLETED|              |
                    |     |DONG JONGKHLA (KUT VILLAGE)
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawryngkneng Block|02-03|CONST. OF DAM AT MAWPYRSHONG   | Rs.   50,000.00   | Rs.   50,000.00   |Completed|              |
                    |     |VILLAGE                        |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawryngkneng Block|02-03|CONST. OF SCHOOL BUILDING OF   | Rs.   30,000.00   | Rs.   30,000.00   |Completed|              |
                    |     |RCLP SCHOOL THADAN             |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawkynrew Block   |02-03|CONST. OF LYNSHING PLAYGROUND  | Rs. 1,00,000.00   | Rs. 1,00,000.00   |         |              |
                    |     |                               |    30/06/2003     |                   |completed|              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawkynrew Block   |02-03|CONST. OF SYNTUNG PLAYGROUND   | Rs. 1,00,000.00   | Rs. 1,00,000.00   |         |              |
                    |     |                               |    30/06/2003     |                   |completed|              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawkynrew Block   |02-03|CONST. OF MADAN THANGSNING     | Rs. 1,00,000.00   | Rs. 1,00,000.00   |Completed |             |
                    |     |L.P SCHOOL AT MADAN THANGSNING |                   |                   |          |
                    |     |(KHYRIM SYIEMSHIP)             |                   |                   |          |             |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawkynrew Block   |02-03|CONST.OF APROACH RD FROM SMIT  | Rs. 1,00,000.00   | Rs. 1,00,000.00   |Completed|              |
                    |     |MAWLAT ROAD TO JOHN'S HERBAL   |                   |                   |         |              |
                    |     |NURSING CARE AT THANGSNING     |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Mawkynrew Block   |02-03|IMPROVEMENT OF FOOTBALL FIELD  | Rs.   20,000.00   | Rs.   20,000.00   |         |              |
                    |     |AT RANGPHLANG                  |                   |                   |completed|              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Laitkroh Block    |02-03|COMPLETION OF VOCATIONAL       | Rs. 1,00,000.00   | Rs. 1,00,000.00   |Completed|              |
                    |     |TRAINING SCHOOL AT LAITLYNGKOT |                   |                   |         |              |
                    |     |UNDER LYNGKYRDEM DEVELOPMENT   |                   |                   |         |              |
                    |     |ASSOCIATION                    |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Laitkroh Block    |02-03|PURCHASE INSTALLATION OF 5     | Rs. 4,40,000.00   | Rs.3,36,000/-     |Completed                |                   
                    |     |COMPUTERS HARDWARE SOFTWARE    |                   |                   |         |
                    |     |SYSTEM, FURNITURE & TRAININ    |                   |                   |         |
                    |     |OF 2 TEACHERS AT LAITLYNGKOT   |                   |                   |         |
                    |     |SECONDARY SCHOOL, LAITLYNGKOT  |                   |                   |         |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Laitkroh Block    |02-03|CONST. OF VOCATIONAL TRAINING  | Rs. 1,00,000.00   | Rs. 1,00,000.00   |Completed               |   
                    |     |SCHOOL AT LAITLYNGKOT          |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------
  Laitkroh Block    |02-03|PURCHASE OF EQUIPMENTS AND     | Rs.   50,000.00   | Rs.50,000/-        Completed               |    
                    |     |ACCESSORIES FOR MULTIPURPOSE   |                   |                   |         |
                    |     | SOCIAL WELFARE ORGANISATION,  |                   |                   |         |
                    |     |MAWJRONG                       |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
                    |     |                               |                   |                   |         |              |
 ------------------------------------------------------------------------------------------------------------------------------------------------------